Bolivia lets public works contracts be repriced, but leaves each agency to find the money

Supreme Decree No. 5775 of 16 November 2026

Public works illustrated with an excavator, a bridge, construction materials and a tape measure.

Rising diesel prices have done to Bolivian public works what one would expect in a sector that runs on heavy machinery. Materials have become dearer, contractors' margins have narrowed and projects have stalled half-built. Supreme Decree No. 5775, signed on 16 November, is the government's response. As an exceptional measure, it allows public bodies to adjust the prices of materials, machinery, equipment and diesel in works contracts, to grant additional advances or pay for materials held in storage, and to increase the value of technical supervision contracts.

This is not the first attempt. The decree itself refers to three recent predecessors with the same aim, Supreme Decrees No. 5321 of January 2025, No. 5406 of May 2025 and No. 5597 of March 2026. What is new is the method. For longer contracts, repricing is no longer a one-off fix but a polynomial formula applied until the works are finished. The Ministry of Public Works has presented it as a way to stop issuing one decree after another.

Who is covered

The decree applies to works and technical supervision contracts signed by public bodies under the Basic Rules of the Goods and Services Administration System (NB-SABS) before it took effect, whether under way or still awaiting the order to proceed. Tenders already awarded may use it once the contract is signed. Procurements in progress or about to start may also do so if they are governed by the NB-SABS, are externally financed and are signed after the decree took effect, with no need for the governing authority to approve changes to the tender documents. Bodies with their own procurement rules may choose between those rules and this regime.

Every mechanism is implemented through one or more amendment agreements, backed by technical, financial and legal reports, which may exceed the amendment percentages set by the NB-SABS. They must be signed by 31 December 2027. The Sixth Additional Provision extends the same deadline to price-adjustment amendments in urban cleaning contracts under Supreme Decree No. 5660.

The 540-day line

The method depends on the original execution period. For contracts of up to 540 calendar days, the adjustment is made once and applies to the price of materials shown in the B-2 unit-price analysis form, excluding indirect costs. It covers only the work still to be done, so inputs bought or used before the amendment are left out. Diesel is adjusted through its cost as an input for machinery and equipment.

For contracts of more than 540 days, the rule changes character. The contractor and the supervisor build a polynomial formula with a fixed, non-adjustable coefficient and no more than seven critical inputs, chosen from the highest-value items that together account for up to 70% of the contract. The formula applies until the contract ends. Price data will come first from the National Statistics Institute (INE) and, where it publishes none, from quotations that the contracting body must verify. The Ministries of Public Works and of Economy have up to ten working days to approve guidance on the formula, which will be for reference only and whose issue does not delay the decree's entry into force.

For contractors, choosing those seven inputs and their weightings will be the most important negotiation of the amendment. It decides how much of future cost inflation is covered for the rest of the job.

For externally financed projects still out to tender, the Second Transitional Provision has a notable practical effect. Public bodies may apply the decree's mechanisms to contracts that do not yet exist, without asking the governing authority to approve changes to the tender documents. Bidders in those tenders should ask during the clarification stage whether the contracting body intends to use the decree, because that shifts the allocation of price risk over the life of the works and, with it, the right price for the bid.

Cash before price

The decree also tackles a problem repricing alone does not solve, namely the lack of cash to buy inputs. Contractors may choose one of two routes, but not both. Additional advances are reserved for contracts under way, require a prior technical and financial review of all advances already granted, may not exceed the cost of materials, machinery and equipment still to be purchased, require a guarantee of proper use covering 100% of the amount and are repaid through each progress certificate before the final account. Alternatively, the contracting body may pay up to 80% of the cost of materials held in storage, with the remaining 20% due once the materials are installed. In return, the contractor must provide invoices, quality certificates and insurance against loss, theft and deterioration, and remains responsible for custody until installation.

Technical supervision is covered too. If the works run longer, the supervision contract may be increased beyond NB-SABS limits where the site inspector justifies it in a technical and financial report, with a guarantee of 7% of the increase.

A power, not an entitlement

Article 4 makes every amendment subject to the contracting body's financial and budgetary capacity, its technical and legal assessment and the agreement of both parties. The decree allows public bodies to pay more, but does not oblige them to do so or provide the funds. Autonomous regional and municipal governments may allocate extra resources for this purpose, if they have them.

Where the money is not there, the decree offers two ways out. The first is to reduce the scope of the works without impairing their functionality, so that the adjustment applies to what remains. The second, more striking, is to terminate a contract under way where repricing is not viable, an impossibility that may be treated as a fortuitous event. The decision lies with the contracting body but requires the contractor's acceptance. If agreed, the contractor is not listed as barred in the State Procurement System (SICOES) and keeps its performance guarantee, but may not claim damages by any legal route. The same rule applies to the supervisor.

In practice that termination is a trade. The contractor gives up a claim in exchange for a clean exit. The decree does not say what happens if the contractor refuses, so in principle the relationship would remain governed by the contract and the NB-SABS.

Article 8 rules out being paid twice. Works already repriced under earlier decrees may use the new regime only for later price changes, with past adjustments treated as the new baseline.

What is left out

The adjustment covers materials, machinery, equipment and diesel and makes no mention of labour. Builders grouped in Cadeco have already called for a formula that updates every cost component, labour included. Where wage increases or labour shortages weigh on a project, the decree offers no specific route to recognise them.

What to do now

Construction companies with public contracts should review their portfolio now and sort each contract by original term, outstanding work and adjustments received under earlier decrees. Preparing the reports and the guarantee updated to the new total, plus a physical and financial schedule where a new term is agreed, takes time, and the guarantee carries a cost that should be built into the numbers. In long contracts, the technical work on critical inputs and weightings deserves as much care as a bid.

For contracting bodies, the decision is above all a budgetary one. The deadline of 31 December 2027 looks generous, but the ability of each municipality, regional government or ministry to pay will decide which projects are finished and which are scaled back or terminated.

César González, Partner, C.R. & F. Rojas Abogados